Hi,

Fikra4Bokra website 1st milestone delivery date is 4 days away, the work I received so far indicates that completion at that date with quality is nearly impossible. The 1st set of question related to the analysis was received only on Friday, June 13th and was answered Saturday June 14th. This coupled with the earlier raised concern of some team members not fully aware of the SOW document puts a big question mark on the progress of the project.

Regards,

Mustafa